How Long Does Concrete Take to Cure? 7 Days Moist, 28 Days to Strength
Keep new concrete moist for 5 to 7 days, and count on its full design strength at 28 days. Quikrete’s Concrete Mix data sheet says to cure for 5 days at 70°F or warmer and 7 days at 50°F to 70°F; NRMCA puts curing at typically 3 to 7 days. You can walk on a standard slab after about 24 hours and drive a car on it after 3 days; heavier vehicles wait 7.
Sources: Quikrete 1101 data sheet, NRMCA CIP 11, Sakrete High-Strength data sheet, ACI FAQ on 28-day strength, FHWA-HRT-05-038. Read 23 October 2026.
- Walk on it24 hoursSakrete High-Strength: open to foot traffic in 24 hours. Sakrete
- Drive a car on it3 daysSakrete High-Strength: vehicular traffic in 72 hours. FHWA's 2006 summary of ACI 330R-92 (parking lots): at least 3 days for cars above 16°C (61°F). Sakrete
- Stop keeping it moist7 daysQuikrete: cure for 5 days at 70°F or higher, 7 days at 50°F to 70°F (50°F to 70°F selected). NRMCA: typically 3 to 7 days. Quikrete
- Heavier vehicles (truck, RV)7 daysFHWA's 2006 summary of ACI 330R-92: at least 7 days for all other traffic above 16°C (61°F); TxDOT 2024 opens pavement to all traffic at 7 days. TxDOT
- Specified (design) strength28 daysACI 318-19: specified compressive strength is based on 28-day tests unless the documents say otherwise. American Concrete Institute
- Penetrating or waterproofing sealer30 daysQuikrete Concrete & Masonry Waterproofing Sealer: allow a minimum of 30 days for new concrete to cure first. A cure-and-seal product goes on 4 to 6 hours after placing instead. Quikrete
Strength the maker publishes for this mix: 2,500 psi at 7 days, 4,000 psi at 28 days (Quikrete Concrete Mix No. 1101). Times are the publishers’ stated minimums at the temperatures they state; your contractor’s mix and the weather can lengthen them.
New Concrete: What You Can Do, and When
For a standard mix in mild weather, measured from the pour. Each time is the shortest its publisher states, at the temperature it states.
Curing Is Keeping It Wet, Not Letting It Dry
Concrete hardens because cement reacts with water, not because the water evaporates. Curing means holding moisture and a moderate temperature in the slab while that reaction runs. NRMCA’s Concrete in Practice 11 says curing should begin immediately after placement and finishing, that the concrete should be kept above 50°F, and that concrete in a dry environment can lose as much as 50 percent of its potential strength compared with moist-cured concrete. Alternate wetting and drying, it says, is not an acceptable curing practice.
The usual methods are plastic sheeting (CIP 11 says at least 4 mils thick), wet burlap kept damp, or a liquid curing compound sprayed on after finishing. Covering a 20x20 slab with 6-mil polyethylene costs about $29 in sheeting at Menards’ roll price. In hot weather, NRMCA’s CIP 12 says to continue curing for at least 3 days and notes that concrete cured hot at an early age ends up weaker than the same concrete cured near 70°F.
How Fast Concrete Gains Strength
Makers publish compressive strength at set ages (ASTM C39 cylinder tests). These are lab figures for each bagged mix, not a promise for your slab, but they show the shape: most of the strength comes in the first week, and the rest by 28 days.
- 2 hours400 psi
- 24 hours1,000 psi
- 7 days2,500 psi
- 28 days4,000 psi
The 28-day figure is the one that counts in a contract. The American Concrete Institute notes that under ACI 318-19 the specified compressive strength is based on 28-day tests unless the construction documents say otherwise, and that 3- and 7-day results are used to monitor early strength, not for acceptance. NRMCA’s CIP 35 says compressive strength can vary from 2,500 psi for residential concrete to 4,000 psi and higher in commercial structures. If you are choosing a mix, see 3,000 PSI concrete cost and 4,000 PSI concrete cost.
Cold and Hot Weather Change the Clock
Cold. NRMCA’s CIP 27 defines cold weather as more than 3 days in a row averaging below 40°F. Fresh concrete freezes below about 25°F, and frozen concrete can lose more than half its potential strength. It should be protected until it reaches 500 psi, about two days after placement, and a 20°F drop in concrete temperature roughly doubles setting time. Concrete that will see freeze-thaw cycles should be protected from them until it reaches at least 3,500 psi. Quikrete says to protect its mix from freezing for the first 48 hours and to use plastic and insulating blankets if temperatures are expected below 32°F.
Hot. Heat speeds setting and dries the surface. NRMCA’s CIP 12 says to keep curing for at least 3 days with wet burlap and plastic, a membrane curing compound or water. Pour early in the day and have the curing method ready before the truck arrives.
How Long a Concrete Slab Lasts
There is no published lifespan for a concrete driveway or patio from a primary source. The closest is the NAHB and Bank of America Home Equity Study of Life Expectancy of Home Components (February 2007), a survey of manufacturers, trade associations and researchers. It lists poured footings and foundations as lasting a lifetime if properly built, and concrete flooring at 50+ years. It has no driveway or patio entry and calls its figures a general guideline only.
What shortens a slab’s life is mostly set in the first week: a poorly compacted base (see site prep cost), joints cut too late, and curing skipped or cut short. When a slab has settled or cracked, compare mudjacking against replacement.
Sources and Method
Every time and strength on this page is quoted from the document that publishes it, read 23 October 2026. Where makers disagree (Quikrete says cure 5 to 7 days, Sakrete 3 to 5, NRMCA 3 to 7), we show the longer figure in the planner and name the others. The ACI curing documents (ACI 308 and 308.1) are not free to read, so ACI timings for opening slabs to traffic come from FHWA’s 2006 guide, which summarises the editions current then; we say so wherever we use them. The planner adds those hours to the pour time you enter; it does not model your mix or weather.
- NRMCA: Concrete in Practice 11, Curing In-Place Concrete (rev. 2017)
- NRMCA: Concrete in Practice 12, Hot Weather Concreting (rev. 2014)
- NRMCA: Concrete in Practice 27, Cold Weather Concreting (rev. 2014)
- NRMCA: Concrete in Practice 35, Testing Compressive Strength (rev. 2014)
- NRMCA: Concrete in Practice 6, Joints in Concrete Slabs on Grade
- Quikrete: Concrete Mix No. 1101 data sheet (rev. Oct 2022)
- Quikrete: 5000 High Early Strength Concrete Mix No. 1007 data sheet (rev. Nov 2022)
- Quikrete: Fast-Setting Concrete Mix No. 1004 data sheet
- Quikrete: Concrete & Masonry Waterproofing Sealer No. 8800-05 data sheet (rev. Nov 2020)
- Quikrete: Acrylic Concrete Cure & Seal No. 8730 data sheet (rev. Oct 2020)
- Sakrete: High-Strength Concrete Mix technical data sheet (2023)
- American Concrete Institute: FAQ: Standards for 7-day and 28-day strength test results (citing ACI 318-19 19.2.1.3)
- FHWA: FHWA-HRT-05-038, Guide for Curing Portland Cement Concrete Pavements, Vol. II (Aug 2006)
- TxDOT: 2024 Standard Specifications, Item 360.4.13.1 (opening concrete pavement to traffic)
- NAHB / Bank of America Home Equity: Study of Life Expectancy of Home Components (Feb 2007)