concreteslabcost.comSourced Cost Model · Oct 2026
Updated October 2026

Concrete vs Asphalt, Pavers and Gravel: 2026 Cost Compared

When Baraboo, Wisconsin opened bids in March 2026, 4-inch asphalt came in at $6.85 and $7.84 a square foot and 4-inch concrete at $6.75 to $9.50, from different contractors in the same month. For a home job, a 20×20 concrete patio runs $2,180 to $5,620 in our cost model (October 2026). Gravel is cheapest; we found no primary price for pavers.

Asphalt, 4 in, bids
$6.85+
$6.85 and $7.84 a sq ft
Concrete, 4 in, bids
$6.75+
$6.75 to $9.50 a sq ft
Gravel, 6 in, stone
$0.98+
$0.98 to $1.66 a sq ft
Pavers
No price
No primary source found
Section 01 / Side by Side

Concrete vs Asphalt vs Pavers vs Gravel: What Each Costs

SurfacePriceSourceWhat it covers
Concrete patio, 20×20, 4 in, mesh$2,180 to $5,620Our cost modelInstalled: concrete, delivery, 4-inch stone base, mesh, forms, crew, overhead
Concrete driveway, 20×24, 4 in, mesh$2,590 to $6,520Our cost modelAs the patio, with 4,000 PSI concrete
Concrete sidewalk, 4 in$6.75 to $9.50 / sq ftBaraboo, WI bids, 4 biddersMunicipal unit price, 6,700 sq ft item; the tab does not say whether removal is included
Concrete sidewalk, 6 in$7.00 to $11.96 / sq ftBaraboo, WI bids, 4 biddersSame proposal, 400 sq ft item
Asphalt surface, 2 in$3.92 and $4.50 / sq ftBaraboo, WI bids, 2 biddersPatching contract, 3,000 sq ft item; sawcutting and base prep are separate items
Asphalt surface, 3 in$5.88 and $6.00 / sq ftBaraboo, WI bids, 2 biddersPatching contract, 3,000 sq ft item; sawcutting and base prep are separate items
Asphalt surface, 4 in$6.85 and $7.84 / sq ftBaraboo, WI bids, 2 biddersPatching contract, 3,000 sq ft item; sawcutting and base prep are separate items; laid as two 2-inch lifts
Gravel, 6 in compacted$0.98 to $1.66 / sq ftFour crusher-run price listsStone only; delivery, grading, fabric, edging and compaction extra
Brick or concrete paversNot pricedNo primary source foundGet a quote stating the paver, base depth and edge restraint

The Baraboo prices are what contractors bid the city on 26 March 2026, on items of 400 to 6,700 sq ft. A homeowner’s single job carries setup and travel that a city program spreads over thousands of feet, so expect a home quote above these unit prices. Their value here is that asphalt and concrete were bid in the same city in the same month.

Section 02 / Driveways

Concrete vs Asphalt Driveway: What to Compare

  • Thickness for thickness. Compare a 4-inch asphalt quote with a 4-inch concrete quote. In Baraboo’s bids the 4-inch asphalt item was laid as two 2-inch lifts.
  • The base. Both need a compacted stone base. Ask each contractor how deep, and whether it is in the price.
  • Upkeep. Asphalt is usually sealed and crack-filled through its life; plain concrete is usually left alone apart from joint and crack sealing. Ask each contractor what they recommend and what it costs, since we have no published price for either.
  • Tear-out. Removing an old driveway is its own line. Our removal and replacement page prices it from public bids.

Full concrete driveway prices by size: concrete driveway cost.

Section 03 / Patios

Concrete vs Pavers for a Patio

If you care most aboutConcretePavers
A price you can checkPriced from published inputs: $2,180 to $5,620 for 20×20Quote only; ask for the paver and base spelled out
RepairsA broken section is cut out and repoured; the patch showsIndividual pavers lift and reset
LooksBroom finish; stamped and stained cost more (see stamped concrete)Choice of shape, colour and pattern
WeedsNone through a slab; only at joints and edgesJoints need filling sand and upkeep

Concrete patio prices by size: concrete patio cost.

Section 04 / Gravel

Gravel: the Cheapest Surface, Priced as Stone

For a 6-inch compacted gravel surface our model orders a fifth more loose stone than the finished volume. At $44.00 to $74.75 a cubic yard of crusher run from D & L Supply, JMJ Companies, Golden Landscaping Supply, Yard Works Landscape Supply, the stone is $0.98 to $1.66 per square foot. Delivery, grading, fabric, edging and compaction are extra and we have no published price for them. Gravel needs topping up and regrading; it is not a slab and does not suit a garage floor.

Method / How We Price

How We Price a Slab

Every installed price on this site comes from one model: published ready-mix and materials prices, plus crew hours priced at Bureau of Labor Statistics wages, plus overhead and margin. The low figure uses the lowest published input and our lowest assumption at every step; the high figure uses the highest. The crew hours, overage and margin are our own estimates, not published figures, and are listed below so you can check them against your quote. Worked example: a 20 x 20 ft patio (4-inch, 3,000 PSI, wire mesh, broom finish, 4-inch stone base).

LineLowTypicalHighBasis
Ready-mix concrete$659$754$8964.94 cu yd plus 5 to 10% overage, at published per-yard prices
Delivery and small-load charges$0$35$419Per-truck charges from the same price lists (10 yd per truck)
Crushed-stone base$261$325$4434 in compacted crusher run
Reinforcement$96$96$966x6 10-gauge mesh panels, lapped
Form lumber$30$45$61Perimeter boards, shared across reuses
Crew labour$770$1,332$2,101Crew hours x BLS wages x employer costs
Overhead and margin$363$776$1,60620% to 40% on direct cost
Installed total$2,180$3,360$5,620Rounded to the nearest $10

Not included: excavation and soil haul-off, removing an old slab, permits, pumping, decorative finishes and sealing. Totals are national; the calculators’ state option swaps in that state’s BLS wages and leaves concrete and materials at the published lists.

Published inputs (read 13 October 2026)

Our assumptions (estimates, not published figures)

  • Crew: half cement masons, half laborers.
  • Setup per job: 8 to 16 crew hours (layout, stripping, cleanup).
  • Per 100 sq ft: 4-inch 4 to 7 crew hours, 6-inch 5 to 8.5, 8-inch 6 to 10; add 0.5 to 1 for mesh or 1.5 to 2.5 for rebar.
  • Concrete overage 5% to 10%; base stone ordered at 1.2x its compacted volume; form boards charged at half to all of their price.
  • Overhead and margin 20% to 40% of direct cost.
  • 6-inch and thicker slabs use 4,000 PSI mix; thinner slabs 3,000 PSI.

Sources: BLS OEWS 47-2051 cement masons (May 2025), BLS OEWS 47-2061 construction laborers (May 2025), BLS ECEC, construction (June 2026), ready-mix price lists from Supreme Concrete, Minimix Concrete, Gehring Construction & Ready-Mix, Scenic City Ready Mix, crusher-run prices from D & L Supply, JMJ Companies, Golden Landscaping Supply, Yard Works Landscape Supply, Menards mesh, rebar, lumber and poly prices, City of Baraboo, WI 2026 public works bid tabulation (26 March 2026). All read 13 and 14 October 2026. Crew hours, overage, overhead and margin are our estimates and are listed in the method above.

FAQ

Concrete vs Alternatives FAQ

Not always by much. In the City of Baraboo, Wisconsin's bids opened on 26 March 2026, 4-inch asphalt surface (two 2-inch lifts) came in at $6.85 and $7.84 a square foot, and 4-inch concrete sidewalk at $6.75 to $9.50 from four bidders. Those are municipal unit prices on 3,000 to 6,700 sq ft items, not a homeowner's quote, and the asphalt was a patching contract, but they are one city's prices in the same month. Get both priced on your own driveway.
Related
Reader Questions

Didn't find your answer?

Ask us. A real person reads every question and we answer the ones we can, with sources. If your question would help other readers, we may publish an anonymised version, with your permission. General reference only.

Ask a question[email protected]